LandKBuilders
Architectural plans for a home building project

How long does a building project take?

Typical timescales for extensions, loft conversions, garage conversions and refurbishments, from design and approvals to completion.

Call 07850 623490

The time on site is only part of the story. Design, approvals and lead times for materials all shape when your project starts and finishes.

Before work starts

Drawings usually take a few weeks. A planning application typically takes around eight weeks, and a Lawful Development Certificate a similar time. Structural calculations and Building Regulations approval can run in parallel. If you need party wall agreements, start early, as neighbours have time to respond.

Typical time on site

As a guide, once approvals are in place:

  • Single storey rear extension: around 10 to 14 weeks
  • Double storey extension: around 14 to 20 weeks
  • Loft conversion: around 6 to 10 weeks
  • Garage conversion: around 3 to 5 weeks
  • Full house refurbishment: around 10 to 16 weeks

What can affect the timescale

Weather affects foundations, brickwork and roofing. Lead times on windows, bifold doors, steel and kitchens can be several weeks, so ordering early keeps things moving. Changes made during the build can also add time. Hidden issues, such as unexpected drains or poor ground, may need extra work.

How we keep projects on track

We plan the order of work carefully, order long lead items early and coordinate all trades ourselves. You get a programme at the start and regular updates as the job moves on, so you always know what is happening next.

A typical extension timeline

As an example, a single storey rear extension usually follows this pattern. The first weeks cover setting up, digging and pouring foundations, and any drainage work. Then the walls rise to damp proof course level and the floor slab goes in. Walls are built to roof height, steels are installed and the roof goes on, making the structure watertight. Windows and doors follow, then the opening into the house is formed. First fix electrics and plumbing, plastering, second fix, kitchen fitting and decoration bring the job to completion. Building Control inspects at the key stages along the way.

A loft conversion follows a different order, with scaffolding first, then floor joists and steels, the dormer or roof alterations, windows, the staircase, and finally insulation, plastering and finishing.

Related services

Further reading

Frequently asked questions

When should I book a builder?+

Talk to builders early, ideally while drawings are being prepared, so you can plan the start date around approvals.

Can work continue in winter?+

Most work can, though frost and heavy rain may pause concrete and brickwork for short periods.

Call now