The right order of works for a renovation

The order a home renovation should follow, from survey and strip out to rewiring, plastering, kitchens and decoration, to avoid costly rework.

Call 07850 623490

Doing things in the right order saves money and avoids redoing work. Here is the sequence we follow on most refurbishments.

1. Survey and planning

Start by understanding the house: structure, roof, damp, wiring and plumbing. This shapes the budget and the programme, and highlights consents you may need.

2. Strip out and structural work

Remove old fittings, finishes and anything being replaced. Structural work comes next, such as removing walls, inserting steels, repairing lintels and fixing the roof.

3. First fix

Electricians and plumbers run new cables, pipes and heating before walls are closed up. This is the time to decide where sockets, lights and radiators go.

4. Plastering

Once first fix is done and inspected, walls and ceilings are plastered or boarded. Plaster needs time to dry before decorating.

5. Second fix and installations

Joiners hang doors, fit skirting and architraves. Kitchens and bathrooms go in, and electricians and plumbers fit sockets, switches, taps and radiators.

6. Decoration and flooring

Decoration comes near the end, with flooring last to protect it. A final snag list makes sure everything is finished properly.

  • Mist coat and decoration
  • Flooring and final fixings
  • Testing certificates for electrics and gas
  • Final clean and handover

Living in the house during a renovation

If you stay in the house, plan the work so that at least one bathroom and a basic kitchen are always usable. Working floor by floor or room by room takes longer but makes life easier. Dust barriers, a clear route for trades and a daily tidy up help a great deal. For whole house projects with rewiring, new heating and replastering, many families find it easier to move out for the noisiest weeks, then return once the main work is done.

Common mistakes to avoid

Getting the order wrong often means paying twice. Common mistakes include:

  • Decorating before electrical and plumbing work is finished
  • Fitting a new kitchen before deciding on flooring
  • Leaving window replacement until after plastering
  • Ignoring damp or roof repairs before internal work
  • Ordering bathroom fittings too late, delaying second fix

Planning the budget

Spend first on the things that are hard to change later, such as structure, roof, wiring, plumbing, heating and insulation. Finishes like paint, light fittings and some furniture can be upgraded over time. A contingency for hidden issues is especially important in older homes, where surprises are more common.

Related services

Further reading

Frequently asked questions

Should I fit the kitchen before or after plastering?+

After. Plastering comes first, then the kitchen is fitted during second fix.

Why is flooring left until last?+

To protect it from damage during the rest of the work.