LandKBuilders
Architectural plans for a home building project

Party wall agreements explained

When the Party Wall Act applies to extensions and loft conversions, how to serve notice on neighbours, and what happens if they dissent.

Call 07850 623490

If your project involves a shared wall or digging near a neighbour's foundations, the Party Wall etc. Act 1996 probably applies. Here is how it works.

When the Act applies

Common situations include:

  • Cutting into a party wall for steel beams in a loft conversion
  • Building a new wall on or at the boundary
  • Digging foundations within 3 metres of a neighbour's building and deeper than its foundations
  • Raising or thickening a party wall

Serving notice

You must serve written notice on affected neighbours, usually one or two months before work starts, depending on the type of work. Neighbours can agree, or dissent, in which case a party wall surveyor is appointed.

Party wall awards

If a neighbour dissents, one agreed surveyor or two surveyors prepare a party wall award. This sets out how the work will be done and records the condition of the neighbour's property. The person building usually pays the surveyor fees.

Talk to your neighbours early

A friendly conversation before serving notice often makes the process easier. Explain what you are planning and when, and share drawings if they are interested.

How we help

We advise when the Act is likely to apply and the timing for notices, so the start date is not held up.

Timing your notices

Because notice periods are one or two months, and surveyors may need extra time if a neighbour dissents, it is wise to serve notices as soon as drawings are ready. This keeps the start date from slipping while you wait.

Types of notice

There are three main types of notice. A party structure notice covers work to an existing party wall, such as cutting in steel beams, and needs two months' notice. A line of junction notice covers building a new wall on or at the boundary, with one month's notice. An adjacent excavation notice covers digging foundations near a neighbour's building, also with one month's notice. Notices must include specific information, and drawings are often attached for excavation work.

Protecting both sides

A schedule of condition, recorded before work starts, protects both you and your neighbour. If a crack appears later, the schedule shows whether it was already there. This avoids disputes and helps keep good relations with neighbours.

Related services

Further reading

Frequently asked questions

Does a loft conversion need a party wall notice?+

On a semi or terrace, usually yes, because steels are often set into the party wall.

What if my neighbour does not respond?+

After 14 days without a response, a dispute is deemed to have arisen and surveyors are appointed.

Call now